Here is the current status of version 2 of Thug 1.
I estimated that re-topology would take approximately 4 weeks instead of the initial 2 weeks taking into account lectures and such.
This model has overrun while trying to apply new techniques learnt from the previous model and topology tutorials.

The flow on the ear has improved greatly from the last one, it's relatively clean.

Here is a production schedule, with slots taking into account our lectures, free time, other events etc.
The work slots do vary in time and length but this is a baseline of my schedule.